ORD, Neb. - During the week of June 22nd, progress on the project was substantial. At the June VCHS Board meeting, TSP reported that 23% of the exterior portion of the project was complete.

During the past week the front lobby, rehabilitation services and administration areas were framed in and the exterior stud walls were erected in several areas of the building.

The main gas line was trenched into the new building and plumbing work continues to be completed throughout the building.

The employee parking lot to the south of the building was graded and poured. Work will soon begin on the front drive up canopy, sheeting of the exterior stud walls and pouring the floors in the building.

Despite the recent rains, the project is still on schedule for completion in September 2010.

For more information about the project, contact the Public Relations office at 728-4347.

Comments (0)Add Comment

Write comment

busy
 
JOIN OUR TEAM!

KNLV is actively seeking a full and/or part-time advertising sales representative. Duties include but are not limited to in person, over the phone and online sales of radio and internet advertising.

Click here for more.

Banner
Banner
Banner
Banner

Community Calendar

View Full Calendar
Add New Event

FROM THE EDITOR

Dear Readers,

KNLV wants to know your stories, your news. Please send us your news, no matter how big or how small.

You can send news to knlvnews@yahoo.com.

It's your news.

Thank You,

Andrew Mihm
Editor, KnlvRadio.com 

viagra for sale | viagra order | canadian viagra | viagra without prescription | viagra uk | order cialis | price viagra | viagra for sale in south africa | where to get viagra samples | cheap viagra pills | online pharmacy canada viagra | viagra dose